Issue B1 – Road drainage and gully maintenance
Action Priority Partners Status June 05 Reviewed 12 April 07
Ensure that the agreed cleaning schedules are adhered to Ongoing, annual review Area Co–ordinator's office Schedules under control of Streetcare Revised cleaning schedule agreed at Area Comm in October. Ongoing.
Implement a reporting procedure for unscheduled cleaning Ongoing, annual review Area Co–ordinator's office Schedules under control of Streetcare no change
Take advantage of changes to service management to gain more local control and allocation of resources Ongoing, annual review Area Co–ordinator's office Schedules under control of Streetcare no change
Issue B2 – Dropped Kerbs
Action Priority Partners Status June 05 Reviewed 12 April 07
Ensure that crossing points where dropped kerbs are required have been included in the appropriate schedule for implementation Medium Highways Ongoing schedule within annual budget Majority now completed. Archive next review – PJ
Issue B3 – Footpaths and snickets
Action Priority Partners Status June 05 Reviewed 12 April 07
Ensure that footpaths and snickets are maintained as clear and safe routes for pedestrians through the village Medium Streetscene Schedules controlled by Streetscene See 1 above. Maintenance OK at present. Problems with Holme Grove /Sandholm snicket raised and actioned by CJ. Now OK.
Arrange for a review of street lighting in snickets to ensure that lighting is brought up to standard High Street lighting department BMDC controls lighting reviews & replacements Proposals sent for revision.
Continue support for a safe river crossing that meets all planning guidelines Ongoing BBA Application depends on Harrogate BC New scheme presented by Ramblers/BBA at April 2006 Forum
Issue B4 – Moor Lane paths and pavement
Action Priority Partners Status June 05 Reviewed 12 April 07
Provide a wider pavement on the East side of Moor Lane under the bridge for safer access to and from the station steps and for pedestrians going towards the village and schools from Scalebor, Hag Farm Lane and Moor Lane High Highways Narrow footpath below minimum width Some changes may be part of junction design (see A6), depending on final Station area junction plan. Part of current parking review.
Take any opportunity from further development to ensure that there is adequate footpath access from the Scalebor estate to the village When possible Rights of Way section No existing footpath Footpath from Ron Lawton Crescent to Moor Lane Centre completed. Archive next review – PJ
Provide a footpath from The Wynches to the Moor Road Low Rights of Way No path: access along wide verge only Path completed. Archive next review – PJ
Issue B5 – Village road sweeper
Action Priority Partners Status June 05 Reviewed 12 April 07
Take advantage of delegation of services under Local Area Management to manage an operative to provide a dedicated service to village streets When possible Streetscene Allocation controlled by Streetscene No legislation under consideration
Issue B6 – Village clean–up days
Action Priority Partners Status June 05 Reviewed 12 April 07
Support and obtain funding for volunteer clean-up initiatives Ongoing Shipley Area Committee Informal and irregular Joint with Chamber of Trade. Next due May/June 2007
Issue B7 – Street lighting
Action Priority Partners Status June 05 Review 12 April 07
Ensure that Street Lighting Department has a list of priorities and a schedule for replacing inadequate street lighting Ongoing review Street Lighting Dept. and Area Committee No list. BCC to propose list from Forum comments List sent. No significant response.
Issue B8 – Telecommunication masts
Action Priority Partners Status June 05 Reviewed 12 April 07
Be aware of changes to legislation for the installation and upgrading of masts and the expert opinion on environmental impact, so as to respond accordingly to proposed masts in the area Ongoing review Planning authorities Govt. summary dated December 2004 Response sent to mast at Bradford Road staithe. No activity on this item.
Issue B9 – Verge hardening
Action Priority Partners Status June 05 Reviewed 12 April 07
Replace grass verge with hard standing/pavement. Current Highways None. New item 2007 Manse & Midgley & possibly part Langford Roads programmed for 2007/8